Plan the whole depot, not just the next charge

A winter day at a sample depot

From noon to noon: what the building draws and when the plan charges. Hover over the chart to stop at any quarter hour.

12:00
Time
Day-ahead price
10.43 ct/kWh
Charging
44 kW
Building
102 kW
Solar
29 kW
  • Building
  • Planned charging
  • Lowest-priced third
  • Connection limit

Safety

Six vans, one fuse, no surprises

A workshop and six vans sit on the same 100 A strand. As the workshop's draw climbs, charging gives way evenly and the total stays within the fuse rating.

Illustrative arithmetic, not site data.

Fuse69 kW
Van 111 kW
Van 211 kW
Van 311 kW
Van 411 kW
Van 511 kW
Van 611 kW
  • Workshop: 3 kW
  • Vans
  • Fuse rating: 100 A, 69 kW

Safety

Protection at every level of the site

A depot's power runs through several fuses, not one. We map the electrical layout and plan against each of them, one quarter hour at a time.

Plenty of systems only watch this one: the 400 A connection for the whole site.

Grid connection400 AMeter
  • Sub-distribution A250 AMeter
    • Strand A1 · 6 fleet vans100 A
    • Strand A2 · 6 staff cars100 A
  • Sub-distribution B160 A
    • Strand B1 · 4 fleet vans63 A

Availability

Out of the gate on schedule

A fuse limit can't tell you which van leaves first. The plan knows each departure and how much charge it needs, so waiting for cheaper power is a calculated choice rather than a gamble.

  • Van 1Out at 05:30
  • Van 2Out at 06:00
  • Van 3Out at 06:30
  • Van 4Out at 07:00
  • Van 5Out at 07:30
  • Van 6Out at 08:30

17.1ct/kWh average day-ahead price across the six vans

  • Charging
  • Plugged in

Simplified: real prices with six made-up vans, each scheduled alone. The optimizer also shares every fuse between them.

On the optimizer's full sample day, 1 of 21 sessions finished below target under the plan, against 4 of 21 under dynamic load management.

Cost

Cheap hours do the heavy lifting

Power prices change every 15 minutes. Without a plan, vans charge when they happen to get back, often into the evening peak. With one, most of the energy lands overnight.

  • Charging above 10 kW
  • Idle or below 10 kW

30.1ct/kWh average charging cost

4% of charged energy in the lowest-priced third of the day

  • Power from the grid
  • Connection limit: 277 kW

Cost

The same energy, a much lower peak

Many grid tariffs bill the single busiest quarter hour. Charging as vans arrive creates that spike at dinner time. Spreading the same energy across the night flattens it.

277 kW highest draw at the connection

Cost

Sun first, grid second

Three settings for one bright day. Add a solar forecast and the plan can leave room for midday output instead of only reacting once it arrives.

Illustrative arithmetic, not site data.

33% covered by your own solar

220 kWh charged by 18:00

  • Spare solar
  • Charging

Cost

Stored energy for the priciest hours

A stationary battery works best as part of the same plan as the chargers. On the sample day, it discharges into the afternoon price spike.

66kWh released during the spike

35.9ct/kWh at the top of the spike, 16:45

Bidirectional charging (V2G, V2B) is on the roadmap, with compatible vehicles and chargers.

  • Battery output (scale to 120 kW)
  • Day-ahead price (scale to 40 ct/kWh)

Three connections to get started

Chargers

We link up over OCPP or API, or through your charge point management system. You are not tied to one charger brand.

Meters

Readings from the connection and below, through a Modbus gateway or from meters your CPMS already sees.

Vehicles

State of charge from manufacturer APIs, telematics or fleet software, so we know what each one still needs.

Sample data from the RiDERgy optimizer. It covers one day and is not a forecast. Prices: EPEX day-ahead DE-LU, 15 minutes (energy-charts.info, CC BY 4.0). The fleet, buildings, fuses and tariff adders are made up for this example.

Behind the scenes

The plan refreshes four times an hour

Load, sunshine, prices and departure times all shift during the day. Each new plan starts from the latest picture.

  1. Collect

    Load at each level, state of charge, day-ahead prices and forecasts.

  2. Decide

    Who charges, how fast and when: safety, then availability, then cost.

  3. Dispatch

    Each charge point gets its own charging limit.

Repeats every 15 minutes

  • Stay under every rating

    Each strand, sub-distribution and the connection keeps to its limit.

  • Meet every departure

    Planned around how quickly each battery takes power as it fills.

  • Then find the savings

    Lowest-priced hours, solar and battery first, with peaks kept down.

If a signal goes missing

Vans still need to go out when part of the system is unavailable. If a reading or a link is lost, charging carries on at a reduced limit until it comes back.

Limits stop arriving, so the charger reverts to the limit stored on the charger itself.

Book Demo